Sale Value
₹134,040,155
Budget Value
₹104,898,501
Mat
₹85,549,771
Sub
₹451,251
FW
₹0
P&M
₹1,798,166
PRW
₹17,099,312
Variance
₹1
Activity Name
CS.16.1.6 - Reinf. Steel
BOQ Quantity
1,419.03 MT
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | REINFORCEMENT STEEL-HYSD BARS-FE 500D | 1,419.03 | 1.035 | 57,500.00 | 59,512.50 | 84,450,022.88 | |
| Mat | WIRE-BINDING WIRE-GI | 1,419.03 | 9.000 | 75.00 | 675.00 | 957,845.25 | |
| Mat | PRECAST RCC/PSC ITEMS-COVER BLOCK | 1,419.03 | 1.000 | 100.00 | 100.00 | 141,903.00 | |
| Sub | S/C Hire charges for Automatic Rebar Cutting & Bending Plant | 1,419.03 | 1.015 | 313.30 | 318.00 | 451,250.83 | |
| PRW | L/c Reinforcement - Substructure | 1,419.03 | 1.000 | 6,050.00 | 6,050.00 | 8,585,131.50 | |
| PRW | L/c Steel Loading, unlaoding & shifting from yard to site | 1,419.03 | 1.000 | 200.00 | 200.00 | 283,806.00 | |
| PRW | L/c Lifting charge Reinforcement Steel-4F | 1,419.03 | 29.000 | 200.00 | 5,800.00 | 8,230,374.00 | |
| P&M | Lifting Charges | 1,419.03 | 1.000 | 1,267.18 | 1,267.18 | 1,798,166.44 | |
| 1,419.03 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹73,922.68 | ₹104,898,499.89 | |||||