Item Analysis

Sale Value

₹98,063,360

Budget Value

₹76,743,268

Mat

₹64,507,625

Sub

₹340,259

FW

₹0

P&M

₹1,355,883

PRW

₹10,539,500

Variance

₹1

Activity Name

CS.16.1.4 - Reinf. Steel

BOQ Quantity

1,070.00 MT

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat REINFORCEMENT STEEL-HYSD BARS-FE 500D 1,070.00 1.035 57,500.00 59,512.50 63,678,375.00
Mat WIRE-BINDING WIRE-GI 1,070.00 9.000 75.00 675.00 722,250.00
Mat PRECAST RCC/PSC ITEMS-COVER BLOCK 1,070.00 1.000 100.00 100.00 107,000.00
Sub S/C Hire charges for Automatic Rebar Cutting & Bending Plant 1,070.00 1.015 313.30 318.00 340,259.47
PRW L/c Reinforcement - Substructure 1,070.00 1.000 6,050.00 6,050.00 6,473,500.00
PRW L/c Steel Loading, unlaoding & shifting from yard to site 1,070.00 1.000 200.00 200.00 214,000.00
PRW L/c Lifting charge Reinforcement Steel-4F 1,070.00 18.000 200.00 3,600.00 3,852,000.00
P&M Lifting Charges 1,070.00 1.000 1,267.18 1,267.18 1,355,882.60
1,070.00 0.000 0.00 0.00 0.00
Selected Item Totals: ₹71,722.68 ₹76,743,267.07