Item Analysis

Sale Value

₹104,934,933

Budget Value

₹82,121,054

Mat

₹70,004,036

Sub

₹369,251

FW

₹0

P&M

₹1,471,411

PRW

₹10,276,355

Variance

₹1

Activity Name

CS.16.1.3 - Reinf. Steel

BOQ Quantity

1,161.17 MT

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat REINFORCEMENT STEEL-HYSD BARS-FE 500D 1,161.17 1.035 57,500.00 59,512.50 69,104,129.63
Mat WIRE-BINDING WIRE-GI 1,161.17 9.000 75.00 675.00 783,789.75
Mat PRECAST RCC/PSC ITEMS-COVER BLOCK 1,161.17 1.000 100.00 100.00 116,117.00
Sub S/C Hire charges for Automatic Rebar Cutting & Bending Plant 1,161.17 1.015 313.30 318.00 369,251.48
PRW L/c Reinforcement - Substructure 1,161.17 1.000 6,050.00 6,050.00 7,025,078.50
PRW L/c Steel Loading, unlaoding & shifting from yard to site 1,161.17 1.000 200.00 200.00 232,234.00
PRW L/c Lifting charge Reinforcement Steel-4F 1,161.17 13.000 200.00 2,600.00 3,019,042.00
P&M Lifting Charges 1,161.17 1.000 1,267.18 1,267.18 1,471,411.40
1,161.17 0.000 0.00 0.00 0.00
Selected Item Totals: ₹70,722.68 ₹82,121,053.76