Sale Value
₹159,114,577
Budget Value
₹124,522,060
Mat
₹109,237,936
Sub
₹576,199
FW
₹0
P&M
₹2,296,067
PRW
₹12,411,858
Variance
₹1
Activity Name
CS.16.1.1 - Reinf. Steel
BOQ Quantity
1,811.95 MT
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | REINFORCEMENT STEEL-HYSD BARS-FE 500D | 1,811.95 | 1.035 | 57,500.00 | 59,512.50 | 107,833,674.38 | |
| Mat | WIRE-BINDING WIRE-GI | 1,811.95 | 9.000 | 75.00 | 675.00 | 1,223,066.25 | |
| Mat | PRECAST RCC/PSC ITEMS-COVER BLOCK | 1,811.95 | 1.000 | 100.00 | 100.00 | 181,195.00 | |
| Sub | S/C Hire charges for Automatic Rebar Cutting & Bending Plant | 1,811.95 | 1.015 | 313.30 | 318.00 | 576,199.19 | |
| PRW | L/c Reinforcement - Substructure | 1,811.95 | 1.000 | 6,050.00 | 6,050.00 | 10,962,297.50 | |
| PRW | L/c Steel Loading, unlaoding & shifting from yard to site | 1,811.95 | 1.000 | 200.00 | 200.00 | 362,390.00 | |
| PRW | L/c Lifting charge Reinforcement Steel-4F | 1,811.95 | 3.000 | 200.00 | 600.00 | 1,087,170.00 | |
| P&M | Lifting Charges | 1,811.95 | 1.000 | 1,267.18 | 1,267.18 | 2,296,066.80 | |
| 1,811.95 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹68,722.68 | ₹124,522,059.12 | |||||