Item Analysis

Sale Value

₹3,073,185

Budget Value

₹2,089,822

Mat

₹1,627,500

Sub

₹9,030

FW

₹0

P&M

₹285,891

PRW

₹167,400

Variance

₹0

Activity Name

CS.4.1 - M5 PCC

BOQ Quantity

465.00 Cum

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat READY MIX CONCRETE-M5 GRADE 465.00 1.000 3,500.00 3,500.00 1,627,500.00
PRW L/c for Pouring of concrete - PCC 465.00 1.000 345.00 345.00 160,425.00
PRW L/c Curing of concrete 465.00 1.000 10.00 10.00 4,650.00
PRW L/C for Hacking 465.00 10.000 0.50 5.00 2,325.00
Sub S/c Testing charges 465.00 1.000 10.00 10.00 4,650.00
Sub S/c Curing & other Miscellaneous Works 465.00 0.942 10.00 9.42 4,380.30
P&M Pumping & Lifting Charges 465.00 1.000 614.82 614.82 285,891.30
465.00 0.000 0.00 0.00 0.00
Selected Item Totals: ₹4,494.24 ₹2,089,821.60