Sale Value
₹26,739,598
Budget Value
₹18,182,040
Mat
₹14,385,455
Sub
₹55,923
FW
₹0
P&M
₹1,703,808
PRW
₹2,036,854
Variance
₹0
Activity Name
CS.13.5.B - M45 RCC
BOQ Quantity
2,771.23 Cum
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | READY MIX CONCRETE-M45 GRADE | 2,771.23 | 1.000 | 5,191.00 | 5,191.00 | 14,385,454.93 | |
| PRW | L/c for pouring of RCC Concrete | 2,771.23 | 1.000 | 345.00 | 345.00 | 956,074.35 | |
| PRW | L/c Curing of concrete | 2,771.23 | 1.000 | 10.00 | 10.00 | 27,712.30 | |
| PRW | L/C for Hacking | 2,771.23 | 10.000 | 0.50 | 5.00 | 13,856.15 | |
| Sub | S/c Testing charges | 2,771.23 | 1.000 | 10.00 | 10.00 | 27,712.30 | |
| Sub | S/c Curing & other Miscellaneous Works | 2,771.23 | 1.018 | 10.00 | 10.18 | 28,211.12 | |
| PRW | L/c for Lifting of concrete - PCC/RCC | 2,771.23 | 25.000 | 15.00 | 375.00 | 1,039,211.25 | |
| P&M | Pumping & Lifting Charges | 2,771.23 | 1.000 | 614.82 | 614.82 | 1,703,807.63 | |
| 2,771.23 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹6,561.00 | ₹18,182,040.03 | |||||