Item Analysis

Sale Value

₹27,085,163

Budget Value

₹18,417,478

Mat

₹14,914,154

Sub

₹54,592

FW

₹0

P&M

₹1,663,254

PRW

₹1,785,478

Variance

₹0

Activity Name

CS.13.4.C - M45 RCC

BOQ Quantity

2,705.27 Cum

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat READY MIX CONCRETE-M45 GRADE (INTERNAL) 2,705.27 1.000 5,513.00 5,513.00 14,914,153.51
PRW L/c for pouring of RCC Concrete 2,705.27 1.000 345.00 345.00 933,318.15
PRW L/c Curing of concrete 2,705.27 1.000 10.00 10.00 27,052.70
PRW L/C for Hacking 2,705.27 10.000 0.50 5.00 13,526.35
Sub S/c Testing charges 2,705.27 1.000 10.00 10.00 27,052.70
Sub S/c Curing & other Miscellaneous Works 2,705.27 1.018 10.00 10.18 27,539.65
PRW L/c for Lifting of concrete - PCC/RCC 2,705.27 20.000 15.00 300.00 811,581.00
P&M Pumping & Lifting Charges 2,705.27 1.000 614.82 614.82 1,663,254.10
2,705.27 0.000 0.00 0.00 0.00
Selected Item Totals: ₹6,808.00 ₹18,417,478.16