Sale Value
₹27,085,163
Budget Value
₹18,417,478
Mat
₹14,914,154
Sub
₹54,592
FW
₹0
P&M
₹1,663,254
PRW
₹1,785,478
Variance
₹0
Activity Name
CS.13.4.C - M45 RCC
BOQ Quantity
2,705.27 Cum
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | READY MIX CONCRETE-M45 GRADE (INTERNAL) | 2,705.27 | 1.000 | 5,513.00 | 5,513.00 | 14,914,153.51 | |
| PRW | L/c for pouring of RCC Concrete | 2,705.27 | 1.000 | 345.00 | 345.00 | 933,318.15 | |
| PRW | L/c Curing of concrete | 2,705.27 | 1.000 | 10.00 | 10.00 | 27,052.70 | |
| PRW | L/C for Hacking | 2,705.27 | 10.000 | 0.50 | 5.00 | 13,526.35 | |
| Sub | S/c Testing charges | 2,705.27 | 1.000 | 10.00 | 10.00 | 27,052.70 | |
| Sub | S/c Curing & other Miscellaneous Works | 2,705.27 | 1.018 | 10.00 | 10.18 | 27,539.65 | |
| PRW | L/c for Lifting of concrete - PCC/RCC | 2,705.27 | 20.000 | 15.00 | 300.00 | 811,581.00 | |
| P&M | Pumping & Lifting Charges | 2,705.27 | 1.000 | 614.82 | 614.82 | 1,663,254.10 | |
| 2,705.27 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹6,808.00 | ₹18,417,478.16 | |||||