Sale Value
₹19,238,148
Budget Value
₹13,081,742
Mat
₹10,878,833
Sub
₹39,010
FW
₹0
P&M
₹1,108,840
PRW
₹1,055,059
Variance
₹0
Activity Name
CS.13.3.D - M55 RCC
BOQ Quantity
1,803.52 Cum
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | READY MIX CONCRETE-M55 GRADE (INTERNAL) | 1,803.52 | 1.000 | 6,032.00 | 6,032.00 | 10,878,832.64 | |
| PRW | L/c for pouring of RCC Concrete | 1,803.52 | 1.000 | 345.00 | 345.00 | 622,214.40 | |
| PRW | L/c Curing of concrete | 1,803.52 | 1.000 | 10.00 | 10.00 | 18,035.20 | |
| PRW | L/C for Hacking | 1,803.52 | 10.000 | 0.50 | 5.00 | 9,017.60 | |
| Sub | S/c Testing charges | 1,803.52 | 1.000 | 10.00 | 10.00 | 18,035.20 | |
| Sub | S/c Curing & other Miscellaneous Works | 1,803.52 | 1.163 | 10.00 | 11.63 | 20,974.94 | |
| PRW | L/c for Lifting of concrete - PCC/RCC | 1,803.52 | 15.000 | 15.00 | 225.00 | 405,792.00 | |
| P&M | Pumping & Lifting Charges | 1,803.52 | 1.000 | 614.82 | 614.82 | 1,108,840.17 | |
| 1,803.52 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹7,253.45 | ₹13,081,742.14 | |||||