Item Analysis

Sale Value

₹28,559,535

Budget Value

₹19,419,645

Mat

₹16,318,189

Sub

₹58,515

FW

₹0

P&M

₹1,663,254

PRW

₹1,379,688

Variance

₹0

Activity Name

CS.13.2.C - M55 RCC

BOQ Quantity

2,705.27 Cum

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat READY MIX CONCRETE-M55 GRADE (INTERNAL) 2,705.27 1.000 6,032.00 6,032.00 16,318,188.64
PRW L/c for pouring of RCC Concrete 2,705.27 1.000 345.00 345.00 933,318.15
PRW L/c Curing of concrete 2,705.27 1.000 10.00 10.00 27,052.70
PRW L/C for Hacking 2,705.27 10.000 0.50 5.00 13,526.35
Sub S/c Testing charges 2,705.27 1.000 10.00 10.00 27,052.70
Sub S/c Curing & other Miscellaneous Works 2,705.27 1.163 10.00 11.63 31,462.29
PRW L/c for Lifting of concrete - PCC/RCC 2,705.27 10.000 15.00 150.00 405,790.50
P&M Pumping & Lifting Charges 2,705.27 1.000 614.82 614.82 1,663,254.10
2,705.27 0.000 0.00 0.00 0.00
Selected Item Totals: ₹7,178.45 ₹19,419,645.43