Sale Value
₹28,559,535
Budget Value
₹19,419,645
Mat
₹16,318,189
Sub
₹58,515
FW
₹0
P&M
₹1,663,254
PRW
₹1,379,688
Variance
₹0
Activity Name
CS.13.2.C - M55 RCC
BOQ Quantity
2,705.27 Cum
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | READY MIX CONCRETE-M55 GRADE (INTERNAL) | 2,705.27 | 1.000 | 6,032.00 | 6,032.00 | 16,318,188.64 | |
| PRW | L/c for pouring of RCC Concrete | 2,705.27 | 1.000 | 345.00 | 345.00 | 933,318.15 | |
| PRW | L/c Curing of concrete | 2,705.27 | 1.000 | 10.00 | 10.00 | 27,052.70 | |
| PRW | L/C for Hacking | 2,705.27 | 10.000 | 0.50 | 5.00 | 13,526.35 | |
| Sub | S/c Testing charges | 2,705.27 | 1.000 | 10.00 | 10.00 | 27,052.70 | |
| Sub | S/c Curing & other Miscellaneous Works | 2,705.27 | 1.163 | 10.00 | 11.63 | 31,462.29 | |
| PRW | L/c for Lifting of concrete - PCC/RCC | 2,705.27 | 10.000 | 15.00 | 150.00 | 405,790.50 | |
| P&M | Pumping & Lifting Charges | 2,705.27 | 1.000 | 614.82 | 614.82 | 1,663,254.10 | |
| 2,705.27 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹7,178.45 | ₹19,419,645.43 | |||||