Sale Value
₹25,615,741
Budget Value
₹17,418,044
Mat
₹14,270,370
Sub
₹55,476
FW
₹0
P&M
₹1,690,177
PRW
₹1,402,021
Variance
₹0
Activity Name
CS.13.2.B - M45 RCC
BOQ Quantity
2,749.06 Cum
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | READY MIX CONCRETE-M45 GRADE | 2,749.06 | 1.000 | 5,191.00 | 5,191.00 | 14,270,370.46 | |
| PRW | L/c for pouring of RCC Concrete | 2,749.06 | 1.000 | 345.00 | 345.00 | 948,425.70 | |
| PRW | L/c Curing of concrete | 2,749.06 | 1.000 | 10.00 | 10.00 | 27,490.60 | |
| PRW | L/C for Hacking | 2,749.06 | 10.000 | 0.50 | 5.00 | 13,745.30 | |
| Sub | S/c Testing charges | 2,749.06 | 1.000 | 10.00 | 10.00 | 27,490.60 | |
| Sub | S/c Curing & other Miscellaneous Works | 2,749.06 | 1.018 | 10.00 | 10.18 | 27,985.43 | |
| PRW | L/c for Lifting of concrete - PCC/RCC | 2,749.06 | 10.000 | 15.00 | 150.00 | 412,359.00 | |
| P&M | Pumping & Lifting Charges | 2,749.06 | 1.000 | 614.82 | 614.82 | 1,690,177.07 | |
| 2,749.06 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹6,336.00 | ₹17,418,044.16 | |||||