Item Analysis

Sale Value

₹53,704,513

Budget Value

₹36,518,273

Mat

₹31,495,528

Sub

₹103,876

FW

₹0

P&M

₹2,880,702

PRW

₹2,038,166

Variance

₹0

Activity Name

CS.13.1.F - M65 RCC

BOQ Quantity

4,685.44 Cum

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat READY MIX CONCRETE-M70 GRADE (INTERNAL) 4,685.44 1.000 6,722.00 6,722.00 31,495,527.68
PRW L/c for pouring of RCC Concrete 4,685.44 1.000 345.00 345.00 1,616,476.80
PRW L/c Curing of concrete 4,685.44 1.000 10.00 10.00 46,854.40
PRW L/C for Hacking 4,685.44 10.000 0.50 5.00 23,427.20
Sub S/c Testing charges 4,685.44 1.000 10.00 10.00 46,854.40
Sub S/c Curing & other Miscellaneous Works 4,685.44 1.217 10.00 12.17 57,021.80
PRW L/c for Lifting of concrete - PCC/RCC 4,685.44 5.000 15.00 75.00 351,408.00
P&M Pumping & Lifting Charges 4,685.44 1.000 614.82 614.82 2,880,702.22
4,685.44 0.000 0.00 0.00 0.00
Selected Item Totals: ₹7,793.99 ₹36,518,272.51