Sale Value
₹539,616
Budget Value
₹366,927
Mat
₹296,030
Sub
₹1,295
FW
₹0
P&M
₹40,763
PRW
₹28,841
Variance
₹0
Activity Name
CS.13.1.B - M30 RCC
BOQ Quantity
66.30 Cum
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | READY MIX CONCRETE-M30 GRADE | 66.30 | 1.000 | 4,465.00 | 4,465.00 | 296,029.50 | |
| PRW | L/c for pouring of RCC Concrete | 66.30 | 1.000 | 345.00 | 345.00 | 22,873.50 | |
| PRW | L/c Curing of concrete | 66.30 | 1.000 | 10.00 | 10.00 | 663.00 | |
| PRW | L/C for Hacking | 66.30 | 10.000 | 0.50 | 5.00 | 331.50 | |
| Sub | S/c Testing charges | 66.30 | 1.000 | 10.00 | 10.00 | 663.00 | |
| Sub | S/c Curing & other Miscellaneous Works | 66.30 | 0.953 | 10.00 | 9.53 | 631.84 | |
| PRW | L/c for Lifting of concrete - PCC/RCC | 66.30 | 5.000 | 15.00 | 75.00 | 4,972.50 | |
| P&M | Pumping & Lifting Charges | 66.30 | 1.000 | 614.82 | 614.82 | 40,762.57 | |
| 66.30 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹5,534.35 | ₹366,927.41 | |||||