Item Analysis

Sale Value

₹539,616

Budget Value

₹366,927

Mat

₹296,030

Sub

₹1,295

FW

₹0

P&M

₹40,763

PRW

₹28,841

Variance

₹0

Activity Name

CS.13.1.B - M30 RCC

BOQ Quantity

66.30 Cum

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat READY MIX CONCRETE-M30 GRADE 66.30 1.000 4,465.00 4,465.00 296,029.50
PRW L/c for pouring of RCC Concrete 66.30 1.000 345.00 345.00 22,873.50
PRW L/c Curing of concrete 66.30 1.000 10.00 10.00 663.00
PRW L/C for Hacking 66.30 10.000 0.50 5.00 331.50
Sub S/c Testing charges 66.30 1.000 10.00 10.00 663.00
Sub S/c Curing & other Miscellaneous Works 66.30 0.953 10.00 9.53 631.84
PRW L/c for Lifting of concrete - PCC/RCC 66.30 5.000 15.00 75.00 4,972.50
P&M Pumping & Lifting Charges 66.30 1.000 614.82 614.82 40,762.57
66.30 0.000 0.00 0.00 0.00
Selected Item Totals: ₹5,534.35 ₹366,927.41