Sale Value
₹386,809,975
Budget Value
₹302,712,666
Mat
₹267,895,947
Sub
₹1,413,075
FW
₹0
P&M
₹5,630,892
PRW
₹27,772,750
Variance
₹2
Activity Name
CS.7.1.A - Reinf. Steel
BOQ Quantity
4,443.64 MT
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | REINFORCEMENT STEEL-HYSD BARS-FE 500D | 4,443.64 | 1.035 | 57,500.00 | 59,512.50 | 264,452,125.50 | |
| Mat | WIRE-BINDING WIRE-GI | 4,443.64 | 9.000 | 75.00 | 675.00 | 2,999,457.00 | |
| Mat | PRECAST RCC/PSC ITEMS-COVER BLOCK | 4,443.64 | 1.000 | 100.00 | 100.00 | 444,364.00 | |
| Sub | S/C Hire charges for Automatic Rebar Cutting & Bending Plant | 4,443.64 | 1.015 | 313.30 | 318.00 | 1,413,075.30 | |
| PRW | L/c Reinforcement - Substructure | 4,443.64 | 1.000 | 6,050.00 | 6,050.00 | 26,884,022.00 | |
| PRW | L/c Steel Loading, unlaoding & shifting from yard to site | 4,443.64 | 1.000 | 200.00 | 200.00 | 888,728.00 | |
| P&M | Lifting Charges | 4,443.64 | 1.000 | 1,267.18 | 1,267.18 | 5,630,891.74 | |
| 4,443.64 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹68,122.68 | ₹302,712,663.53 | |||||