Item Analysis

Sale Value

₹386,809,975

Budget Value

₹302,712,666

Mat

₹267,895,947

Sub

₹1,413,075

FW

₹0

P&M

₹5,630,892

PRW

₹27,772,750

Variance

₹2

Activity Name

CS.7.1.A - Reinf. Steel

BOQ Quantity

4,443.64 MT

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat REINFORCEMENT STEEL-HYSD BARS-FE 500D 4,443.64 1.035 57,500.00 59,512.50 264,452,125.50
Mat WIRE-BINDING WIRE-GI 4,443.64 9.000 75.00 675.00 2,999,457.00
Mat PRECAST RCC/PSC ITEMS-COVER BLOCK 4,443.64 1.000 100.00 100.00 444,364.00
Sub S/C Hire charges for Automatic Rebar Cutting & Bending Plant 4,443.64 1.015 313.30 318.00 1,413,075.30
PRW L/c Reinforcement - Substructure 4,443.64 1.000 6,050.00 6,050.00 26,884,022.00
PRW L/c Steel Loading, unlaoding & shifting from yard to site 4,443.64 1.000 200.00 200.00 888,728.00
P&M Lifting Charges 4,443.64 1.000 1,267.18 1,267.18 5,630,891.74
4,443.64 0.000 0.00 0.00 0.00
Selected Item Totals: ₹68,122.68 ₹302,712,663.53